Tag: timothy frawley

  • Citrus Heights city hall ‘on target’ for completion by September

    New Citrus Heights city hall, in progress
    An in-progress view of the new Citrus Heights city hall, taken on Jan. 21, 2016. // CH Sentinel

    Updated Jan. 22, 9:44 a.m.–
    Construction of the new $22 million Citrus Heights city hall is “on target” for completion by September of this year, according to the project’s manager and City officials.

    After beginning work on the project last July, Project Manager Tyler Gahagan said structural steel went in earlier this month, followed by a roof being put on the 35,000-square-foot facility last week. Currently, he said crews have started metal stud framing and are installing plumbing and electrical.

    Gahagan said some site work had been slowed down by rain, which caused cement trucks to slip and slide in the mud, but he said the new hall is on track for completion by mid-September.

    The new hall features a single-story design, along with an adjacent 4,000-square-foot utility yard. Its new location is on a 10.9-acre parcel just north of the post office on Fountain Square Drive, about a block away from where the old city hall was located.

    Approved unanimously by councilmembers last March, the new hall project included authorization for Dignity Health to construct a three-story medical office building in place of the old city hall, at the corner of Fountain Square Drive and Greenback Lane. Demolition of the former hall was completed in November, and a groundbreaking ceremony for the new hall was held in July of last year.

    [Related: Citrus Heights leaders break ground on new city hall project]

    According to Monica Alejandrez, who serves as assistant to the city manager, Panattoni Development submitted plans for the new 68,727-square-foot medical building, but a specific start date is unknown. She estimated construction would begin in spring of this year.

    On its website, the City calls the new hall and medical building project “a unique public-private-partnership,” which it says will generate more than 170 jobs and result in a “direct investment of $53.2 million into the Citrus Heights economy.”

    [Image: Click to see official drawing of what the new city hall will look like when complete]

    The new single-story hall will house 65 city employees, who were previously stationed in four separate buildings at the old hall. Staff are currently located in a temporary city hall facility being leased in the Grand Oaks Shopping Center on Auburn Boulevard. The hall was moved in July 2015 to allow for demolition work to begin.

    Background

    The new city hall project caused some controversy among residents during discussion tracing back to 2013, with concerns about increased traffic, construction noise, and whether a new hall was needed. Supporters, like the Citrus Heights Chamber of Commerce and city council members, billed the project as good for jobs and a cost-efficient way to replace an aging hall without incurring debt.

    [Related: Council votes 5-0 for new city hall & MOB; lawsuit threatened]

    The city manager’s office previously released figures saying the net impact of the new hall to the City’s general fund would only be about $8.9 million after 15 years, largely due to a $6.9 million lease agreement with Dignity Health for use of the old hall grounds, as well as projected energy savings from a new, more efficient city hall facility.

    [follow text=”Follow local news:”]

    A lawsuit filed by the group Preserve Our Civic Center is still ongoing against the project, with a Sacramento Superior Court hearing scheduled for April 1, 2016. Norman Hill, a representative for the group, said the lawsuit seeks to stop the project from moving forward, due to alleged violations of the California Environmental Quality Act (CEQA).
    Hill said a "key" issue involved in the lawsuit regards traffic impact from the new medical building and city hall, a "major impact" he believes was "concealed" from the public, in violation of CEQA. Prior requests for comment from city officials regarding the lawsuit have been referred to Ruthann Ziegler, the city attorney for Citrus Heights. Ziegler replied Wednesday afternoon to a Sentinel request seeking the City's perspective and response to the lawsuit, as well as if progress had been delayed on the project due to the lawsuit. In a short email statement, she said "progress on both the MOB and the new city hall is continuing," but did not comment on the lawsuit. [Related: Judge denies motion to halt Citrus Heights city hall demolition] Last July, Judge Timothy Frawley denied a motion from Hill's group which sought to temporarily bar the City of Citrus Heights from proceeding with plans to demolish the old city hall. Although that attempt was unsuccessful, Hill said he's hopeful "some kind of compromise settlement" can be reached with the City through the legal process, but said specifics couldn't be addressed due to the ongoing nature of the lawsuit.

  • Judge denies motion to halt Citrus Heights city hall demolition

    Judge denies motion to halt Citrus Heights city hall demolition

    view of medical office building on Greenback lane in Citrus Heights
    A computer rendering of the new three-story medical office building on Greenback Lane, approved by Citrus Heights council members on March 26, 2015.

    A Sacramento Superior Court judge denied a motion Friday that sought to temporarily bar the City of Citrus Heights from proceeding with plans to demolish its existing city hall and allow Dignity Health to construct a three-story medical office building (MOB) in its place, according to court documents.

    Norman Hill, who heads up the group suing the City over the MOB and city hall project, said his “Preserve Our Civic Center” group sought a temporary restraining order after learning the City had planned a July 18 “Cash & Carry” day to liquidate various items and decor from the existing hall’s property. He said Judge Timothy Frawley ultimately rejected the group’s motion for a 10-day restraining order, after finding “the balance of the equities came out in favor of the City” and determining such an order would present a “great hardship for the City.”

    City representatives were unavailable for comment by phone and email over the weekend.

    The POCC lawsuit, initially filed in April, asks the court to declare the city council’s March 26 approval of the new hall and MOB project to be “invalid and void,” and that the Environmental Impact Report (EIR) prepared for the project “fails to satisfy the requirements of [the California Environmental Quality Act].” It also asks the court to order a “new legally adequate” EIR for the project, and require suspension of all contracts related to construction on the project until alleged violations of CEQA are addressed, according to court filings.

    [Learn more: Lawsuit filed against Citrus Heights over MOB, new hall]

    Although unsuccessful in temporarily halting progress on the city hall demolition, Hill said his group plans to continue with the lawsuit against the project, estimating it could take until early 2016 to get a final decision from a judge. The retired environmental attorney and Citrus Heights resident said he’s currently awaiting a “big pile” of documents to be released by the City in response to a Public Records Act request.

    Note: this story will be updated Monday to include comments from the City, if reached.
    [follow text=”Follow local news:”]